Municipal Operations Center – Phases III & IV

Design work continues to move forward for Phases 3 and 4 of the Municipal Operations Center project. Staff and project partners are continuing to refine the overall design and work toward establishing final project pricing.

While there have been no major construction-related milestones since the last update, progress is being made behind the scenes as the project advances through the design phase. Updated concepts and renderings continue to provide a visual representation of the planned improvements and overall project vision.

Project Update: May 11, 2026

The Municipal Operations Center project has moved into the schematic drawing phase. The City is also working to finalize the construction contract.
Project Update: April 2, 2026

Design work continues to move forward on the Municipal Operations Center. The project has progressed from basic concept design into more formal drawings for construction and site work. Staff is working to advance the design as far as possible within the current contract budget, with the goal of delaying a change order for additional design costs until the next fiscal year.

Project Update: March 1, 2026

Design work continues to make steady progress. The floor plan for the new administrative building is nearing completion. Discussions are ongoing to determine pricing based on project needs versus additional desired features.

Project Update: October 30, 2025

Municipal Operations Center (MOC) – Phases III & IV

Location: 915 Winston Avenue

Overview:

With Phases 1 and 2 now complete, the City of Statesville is preparing to advance the next stages of the Municipal Operations Center (MOC) project. These phases continue the City’s long-term effort to centralize and modernize essential Public Works and Public Utilities operations.

Phase 3 includes the renovation of the existing Fleet Maintenance building - recently vacated after Phase 2 - to house the Warehouse Division. Planned improvements include upgraded lighting, HVAC, plumbing, flooring, shelving, and other building systems, as well as minor sitework adjacent to the building.

Phase 4 involves demolishing the existing administration building and constructing a new facility to accommodate the Public Works and Public Utilities operations divisions. Renovation of the current building may be considered if cost and functionality are determined to be comparable. Temporary relocation of administrative staff will be necessary during this phase.

Key Features & Benefits to Residents:

The new and renovated facilities will provide an improved, efficient workspace for City staff - supporting enhanced coordination and faster response times as employees continue to serve the residents of Statesville.

Project Timeline

  • Anticipated Start Date: Summer 2026
  • Anticipated Completion Date: TBD
  • Current Phase: Design Stage

Estimated Cost & Funding

  • Estimated Cost: $15,000,000
  • Funding Source: City of Statesville

Potential Disruptions:

Minimal disruptions are expected during design and construction. Temporary relocation of staff and internal transitions will occur as part of the project’s phasing.

City of Statesville Celebrates Completion of Phases I & II at the Municipal Operations Center: July 16, 2025

The City of Statesville held a ribbon cutting ceremony today to celebrate the official opening of Phases I and II of the new Municipal Operations Center (MOC), located at 1105 Winston Avenue. The event was attended by members of City Council, City staff, and representatives from Wharton Smith, the contractor overseeing the project.

This milestone marks the completion of several key components of the MOC project. Phase I includes the new Statesville Public Power building, which provides expanded office space, updated infrastructure, and covered parking to support the City’s electric utility operations. Phase II features a modern Vehicle Maintenance Garage, designed to enhance fleet servicing capacity, improve safety, and increase efficiency, and also adds a centralized warehouse that streamlines storage and access to parts, tools, and materials used by various departments.


Construction on the Municipal Operations Center began in November 2023. The total cost of the multi-phase project is approximately $23 million and is fully funded by the City of Statesville. Departments are currently in the process of moving into the new facilities and preparing the spaces for full operation.

The MOC is part of a long-term initiative to consolidate City operations into a central campus, improve coordination among departments, and better serve the community through faster, more efficient responses. With the first two phases now complete, planning is underway for Phases III and IV, which will house facilities for Public Utilities, Public Works, and Stormwater operations.

Project Update: June 2, 2025

The Municipal Operations Center remains on track for move-in by mid-June. Crews have made steady progress, and one of the latest milestones includes the installation of signage on the buildings – and it looks great! The new signs not only mark the facility’s presence but also reflect the City’s pride in this modern, consolidated operations hub.

Check back soon for more updates as we approach the official opening!

Municipal Operations Center Update
Update: May 2, 2025

Progress continues at the Municipal Services Center, and we're nearing key milestones:

  • The Vehicle Maintenance Garage (VMG) and Public Power Building are on track for occupancy in early May.
  • The Warehouse remains on schedule for completion in early June.

Additional site updates:

  • The final topcoat of asphalt has been installed throughout the facility.
  • Parking spaces at the VMG and Public Power buildings have been striped.
  • Perimeter fencing is now 99% complete, wrapping up one of the final exterior elements of the project.

A ribbon cutting ceremony will be announced soon to celebrate the opening of this important facility.

Stay tuned as we prepare to bring these new facilities online to better serve our community!

Municipal Operations Center Update
Update: March 31, 2025

Progress on the Municipal Operations Center (MOC) remains steady, with key components of the project moving forward on schedule. The Statesville Public Power building and the Vehicle Maintenance Garage are expected to be completed by the end of April or early May, providing modern, efficient spaces for electric utility services and fleet operations. The Warehouse phase is also on track, with completion anticipated in June. Low voltage work across the site is progressing well and should be finalized soon. Recent weather conditions have been favorable and have not caused any delays. Overall, the project is moving along well and will ultimately support the City of Statesville’s goal of enhancing municipal services and operational efficiency.

Municipal Operations Center Update

The City of Statesville is investing in improved efficiency and service delivery with the construction of the Municipal Operations Center (MOC) at 1105 Winston Avenue. This multi-phase project will provide modern facilities for Public Power, Vehicle Maintenance, and essential city services, ensuring that city employees can operate more effectively to serve residents.

Key Features & Community Benefits

  • Phase 1: Statesville Public Power Building & Covered Parking – Enhancing operations for the city’s electric utility services.

  • Phase 2: Vehicle Maintenance Garage – Providing updated facilities for maintaining the city’s fleet, improving efficiency and safety.

  • Phase 3: Warehouse – Centralizing storage for essential equipment and materials.

  • Phase 4: Future Expansion – While not yet designed, this phase will incorporate workspaces for Public Utilities, Public Works, and Stormwater, further streamlining city operations.

  • Improved Service for Residents – Modern buildings and better-equipped facilities will allow city employees to work more efficiently, ensuring faster and more effective service to the community.

Project Timeline & Investment

  • Start Date: November 2023

  • Anticipated Completion: April 2025

  • Estimated Cost: $23 million

Funding Sources:

This project is fully funded by the City of Statesville, demonstrating a strong commitment to enhancing municipal operations and infrastructure.

Why This Project Matters

By modernizing the facilities that support public utilities, maintenance, and city services, the Municipal Operations Center will help ensure that Statesville remains efficient, responsive, and prepared for future growth. This investment will result in improved service delivery, reduced operational delays, and a more streamlined approach to city-wide infrastructure management.

Image Gallery

Have questions regarding this project? Please complete the contact form below to learn more.

Contact the Construction & Project Manager, Engineering