Sidewalk Project
Stockton & Alexander Streets

Project Update: June 1, 2026

Construction continues on the Stockton Street and Alexander Street Sidewalk Project, with significant progress made along Alexander Street.

On Alexander Street, sidewalk installation has been completed from the intersection of Alexander Street and Deaton Street to the intersection of Alexander Street and North Lackey Street. Crews are continuing sidewalk construction down the hill toward Nursery Lane. Tree removal is ongoing where necessary to accommodate the project, and stumps that interfered with the sidewalk ramp at the corner of Alexander Street and North Lackey Street have been removed.

On Stockton Street, tree removal activities have begun in preparation for construction. Sidewalk installation along this portion of the project is expected to begin within the next two weeks.

Project Update: May 11, 2026

The Stockton and Alexander sidewalk project continues to progress well. Sidewalk installation has now been completed from Deaton Street to Wilson Street.

Project Update: April 10, 2026

Work is scheduled to begin on Monday, April 13 along Alexander Street, starting at the intersection of Deaton Street and progressing east toward Oakland Avenue. During this phase of construction, traffic along Alexander Street will be reduced to one lane intermittently over the next couple of weeks as crews continue work in the area. Motorists are encouraged to use caution, watch for crews and equipment, and allow extra travel time when passing through the work zone.
Project Update: January 2026

This project is currently scheduled to begin March 2026. Construction timing is dependent on weather conditions, as certain phases of the work require consistently warm temperatures.

If an extended period of warmer weather is forecast and realized, the contractor may be able to begin work sooner. At this time, colder winter temperatures remain the primary factor limiting an earlier start.

Additional updates will be shared as the project start date approaches or if conditions allow for an earlier mobilization.

Sidewalk Project – Stockton & Alexander Streets
September 10, 2025

Location: Stockton Street from Holland Drive to Brookdale Drive and Alexander Street from Deaton Street to Nursery Lane

Project Overview

The Sidewalk Project on Stockton and Alexander Streets will provide continuous sidewalk coverage along two key stretches of roadway. The contractor will grade and install new sidewalk sections, making these streets safer and more accessible for residents.

Key Features

  • The project will fill in missing sidewalk sections on Stockton and Alexander Streets.
  • It will allow residents to walk these stretches of roadway without being in the street.
  • It will increase mobility and pedestrian safety for residents in the area.

Project Timeline & Investment

  • Anticipated Start Date: September 2025
  • Anticipated Completion: November 2025
  • Estimated Cost: $498,080

Funding Sources

This project is funded through Powell Bill funds.

Potential Disruptions

  • There may be some temporary lane closures, but traffic will be able to pass in at least one lane at all times.
  • Construction machinery will create noise during the project.
  • Some landscaping at residences may be disturbed due to its location within the right of way.

Why This Project Matters

The Sidewalk Project will improve pedestrian safety and connectivity by filling in missing sections of sidewalk along Stockton and Alexander Streets. This investment creates safer walking routes, supports neighborhood mobility, and enhances quality of life for residents in the area.

View the final Stockton Street renderings here

View the final Alexander Street redurings here


Have questions regarding this project? Please complete the contact form below to learn more.