Statesville Regional Airport: Apron Expansion

Project Update: May 11, 2026

The construction grant for the Airport Apron Expansion project is scheduled to go before the North Carolina Department of Transportation Board for approval in June.

Project Update: March 1, 2026

The project is currently in the design phase, with design completion anticipated by the end of March. Once finalized, the project will be submitted to NCDOT Aviation to secure the construction grant.

Statesville Regional Airport: Apron Expansion
August 2025

Location: Statesville Regional Airport

Project Overview

The Airport Apron Expansion Project will expand aircraft parking apron space at the Statesville Regional Airport. This expansion will also allow for the future construction of two additional hangars, further enhancing the airport’s capacity to serve aircraft owners and operators.

Key Features

  • The project will provide additional apron space to accommodate two future hangars.
  • It will create new tie-down spots for aircraft, supporting airport operations and growth.

Project Timeline & Investment

  • Anticipated Start Date: April 2026
  • Anticipated Completion: November 2026
  • Estimated Cost: $1,745,000

Project Phases

  • Planning and Design: Currently in the design phase

Funding Sources

This project is funded through NC State Aviation funds.

Why This Project Matters

The Airport Apron Expansion will strengthen the long-term growth of the Statesville Regional Airport by creating the infrastructure needed for future hangars and additional aircraft parking. This investment supports the airport’s continued role as a regional economic driver and enhances the capacity and efficiency of aviation services in Statesville.

Have questions regarding this project? Please complete the contact form below to learn more.