2025 Street Resurfacing Project


Project Update: August 29/2025

The 2025 Street Resurfacing Project is now complete.

All designated streets and greenway sections have been successfully resurfaced, providing smoother travel and improved connectivity for the community.


Project Update: August 1, 2025


The Street Resurfacing Project is nearing completion! The contractor is finishing up the final phases, with only two streets remaining - portions of Old Charlotte Road and West Sharpe Street. In addition to the remaining roadwork, crews will also be paving eight locations along the Greenway to improve accessibility and user experience. Thank you for your continued patience as we wrap up this project. We look forward to providing smoother, safer streets and greenway paths for everyone to enjoy.

Project Update - June 25, 2025

The City of Statesville continues its 2025 Street Resurfacing Program, and we appreciate the community’s continued patience as we navigate schedule adjustments due to weather and site conditions. Below is the updated paving schedule for this week and next:

  • Wednesday, June 25: Crews will complete paving on Beauty Street and begin paving on Walton Drive.
  • Thursday & Friday, June 26–27: Paving will continue on Stonecrest, Stony Lane, and Boulder Place.
  • Monday, June 30: This day is being held open in case work is not completed on Stonecrest, Stony Lane, or Boulder Place.
  • Tuesday & Wednesday, July 1–2: No paving scheduled.

The paving contractor has been placing electronic sign boards and distributing door hangers (as needed) to notify residents ahead of work on each street.

Thank you again for your understanding as we move through this important infrastructure improvement. The final product is looking great, and we’re excited to continue making progress across our neighborhoods.

Project Update - June 16, 2025

Paving operations for the City of Statesville’s 2025 Street Resurfacing Project are scheduled to begin Monday, June 16, and continue for approximately ten weeks.

We’ve completed the pre-construction meeting and finalized the first week’s paving schedule. The following streets are planned for resurfacing this week (weather permitting):

  • June 16 – Pecan Street (full street closure will be required)
  • June 17 – 3rd Creek Wastewater Treatment Plant area
  • June 18 – Shannon Court
  • June 19–20 – Lindsey Street, Hazelwood Drive, Cunningham Drive, and Dillon Drive

Residents will be notified at least 48 hours in advance of paving through door hangers and message boards, and appropriate traffic control will be in place to ensure public safety.

Please note: Although Thursday, June 19 is a city holiday, paving operations will continue.

Thank you for your patience and cooperation as we work to improve our streets.

The Annual Street Resurfacing Project is a key infrastructure improvement initiative aimed at resurfacing roads and sections of greenways throughout Statesville. This project will enhance roadway quality, improve pedestrian pathways, and extend the lifespan of city streets, ensuring a smoother and safer travel experience for residents and visitors.

February 5, 2025

Key Features & Community Benefits

  • Road & Greenway Resurfacing – Restoring and improving various streets and greenway sections throughout the city.

  • Enhanced Roadway Conditions – Reducing wear and tear on vehicles and creating safer streets for drivers, cyclists, and pedestrians.

  • Temporary Closures & Construction Work – Heavy equipment will be milling and paving streets, requiring some temporary closures.

  • Long-Term Infrastructure Improvement – A more durable and well-maintained road and greenway system for the community.

Project Timeline & Investment

  • Anticipated Start Date: Early Spring 2025

  • Anticipated Completion: June 2025

  • Estimated Cost: $1,200,000

Funding Sources

  • Powell Bill Funds – Contributing to project costs

  • City of Statesville – Providing additional funding

Why This Project Matters

Well-maintained roads and greenways are essential for safe and efficient transportation. The Annual Street Resurfacing Project will enhance infrastructure, improve travel conditions, and support long-term sustainability in Statesville’s transportation network.

2025 Statesville Street Resurfacing Map

Image Gallery

Have questions regarding this project? Please complete the contact form below to learn more.

Contact the Public Works Director

Latest City of Statesville News:

Road Closures Scheduled on June 19 and 20, 2026 for Comm... The City of Statesville has approved special event permits for two community celebrations taking place on June 19 and June 20, 2026. As ...
Statesville Design Review Committee June 18, 2026 Meetin... AGENDA DATE: June 8, 2026 TO: Statesville Design Review Committee CC: Erika Martin, Planning Director; Harman Caulder, Assistant Plannin...
A North Carolina drought monitor map dated June 2, 2026, shows drought conditions across the state. Much of central and northern North Carolina remains in severe to extreme drought, indicated by orange and red shading. Areas of western North Carolina and portions of the coastal region are experiencing moderate drought, shown in tan. A small area in the southeastern corner of the state remains in extreme drought. The map includes drought classification categories ranging from abnormally dry (D0) to exceptional drought (D4), along with logos from the USDA, NDMC, NOAA, and other monitoring agencies.
City of Statesville Moves to Stage 2 Water RestrictionsThe City of Statesville is currently under Stage 3 (Extreme Drought) conditions. Beginning at 8 a.m. on May 4, 2026, the City will enfor...

View More