Project Update: August 1, 2025
The Street Resurfacing Project is nearing completion! The contractor is finishing up the final phases, with only two streets remaining - portions of Old Charlotte Road and West Sharpe Street. In addition to the remaining roadwork, crews will also be paving eight locations along the Greenway to improve accessibility and user experience. Thank you for your continued patience as we wrap up this project. We look forward to providing smoother, safer streets and greenway paths for everyone to enjoy.
The City of Statesville continues its 2025 Street Resurfacing Program, and we appreciate the community’s continued patience as we navigate schedule adjustments due to weather and site conditions. Below is the updated paving schedule for this week and next:
The paving contractor has been placing electronic sign boards and distributing door hangers (as needed) to notify residents ahead of work on each street.
Thank you again for your understanding as we move through this important infrastructure improvement. The final product is looking great, and we’re excited to continue making progress across our neighborhoods.
Paving operations for the City of Statesville’s 2025 Street Resurfacing Project are scheduled to begin Monday, June 16, and continue for approximately ten weeks.
We’ve completed the pre-construction meeting and finalized the first week’s paving schedule. The following streets are planned for resurfacing this week (weather permitting):
Residents will be notified at least 48 hours in advance of paving through door hangers and message boards, and appropriate traffic control will be in place to ensure public safety.
Please note: Although Thursday, June 19 is a city holiday, paving operations will continue.
Thank you for your patience and cooperation as we work to improve our streets.
Key Features & Community Benefits
Road & Greenway Resurfacing – Restoring and improving various streets and greenway sections throughout the city.
Enhanced Roadway Conditions – Reducing wear and tear on vehicles and creating safer streets for drivers, cyclists, and pedestrians.
Temporary Closures & Construction Work – Heavy equipment will be milling and paving streets, requiring some temporary closures.
Long-Term Infrastructure Improvement – A more durable and well-maintained road and greenway system for the community.
Project Timeline & Investment
Anticipated Start Date: Early Spring 2025
Anticipated Completion: June 2025
Estimated Cost: $1,200,000
Funding Sources
Powell Bill Funds – Contributing to project costs
City of Statesville – Providing additional funding
Why This Project Matters
Well-maintained roads and greenways are essential for safe and efficient transportation. The Annual Street Resurfacing Project will enhance infrastructure, improve travel conditions, and support long-term sustainability in Statesville’s transportation network.